An aging road gets revamped with roundabouts.

Outdated and experiencing significant erosion, Kapur helped modernize WIS 181 by providing preliminary and final design for the milling and resurfacing of 2.9 miles of this rural roadway.

Two new roundabouts and two new crosswalks and their associated ramps were constructed, along with the design and replacement of the existing guardrails and culvert pipes.

To minimize the project’s impact on motorists, Kapur completed a comprehensive plan review and developed a detour plan, construction staging plan, and multi-stage traffic control to maintain pedestrian access. 

Services
  • Agency coordination
  • Alternative analysis
  • Design study report
  • Drainage design
  • Environmental document (CEC)
  • Erosion control
  • Field survey
  • Final roadway design
  • Geometric concepts
  • Lighting design
  • Pavement design report
  • PS&E
  • Public involvement
  • Preliminary roadway design
  • Right-of-way plat
  • Signal design
  • Signing & marking
  • Stormwater management
  • Utility coordination
Resurfaced roadway along a rural stretch of WIS 181.
The replaced guardrail along the completed WIS 181 roadway separating the road from the stormwater drainage areas.
Vehicles driving on the completed roadway with new pavement, markings, and signage.
The replaced guardrail along a stretch of the completed WIS 181 roadway.
One of the completed roundabouts for the WIS 181 reconstruction.
One of the replaced culvert pipes under the roadway used for stormwater management.